Nov 8, 2026 · Research
How often does a power date come true?
New large-load sites in Texas met 13 of 59 first power dates. Half waited 221 days or more past the date for power.
Read the brief
Nov 8, 2026 · Research
New large-load sites in Texas met 13 of 59 first power dates. Half waited 221 days or more past the date for power.
Read the brief

New large-load sites in Texas met 13 of 59 first power dates. Half waited 221 days or more past the date for power.

Utilities serving new data centers and their customers carry the cost. PJM asked for comments by November 30 and a FERC order by January 29.

PJM files the new cost split with federal regulators by October 29. Each utility’s share is set from the large loads it reports a week before bidding opens, and then it does not move.

ERCOT’s August report identified 17 projects awaiting energization approval. A separate proposal would begin transmission billing when capacity becomes available.

FERC accepted and suspended the backstop procurement, rejected interim service, and retained the large load registry.
SPP’s large load rules face federal review. NERC’s separate registry proposal is now at FERC.

The adopted rule permits forfeiture when supporting documents cannot verify information. The remedy is discretionary; audit duties and eligibility paths matter.

A conditional scenario about computing costs, heat removal and grid access, with the June 2026 ERCOT queue as a historical example.

ERCOT’s June 2026 snapshot records 466,497 MW of requests and a 5,700 MW Observed Energized tier. Their 1.2% ratio is not a construction completion rate.
Working notes from our agent-systems experiments. Not energy research.
An archival note on automated research, portfolio decisions and human oversight.
An archival technical note on tool access, protocol design and integration boundaries.
An archival technical note on agent discovery, task exchange and coordination.
An archival technical note on orchestration, state, tool execution and oversight.