Nov 8, 2026 · Research

How often does a power date come true?

New large-load sites in Texas met 13 of 59 first power dates. Half waited 221 days or more past the date for power.

Read the brief
A power plant at night, cooling towers and a stack lit against dark hills.

Next deadlines

All, in your calendar
  1. OCT 29PJM’s conditional refiling window ends
  2. NOV 1ERCOT’s scheduled stability assessment cutoff
  3. NOV 9PJM files its revised large-load registry rules
  4. NOV 20SPP answers FERC on its rules for big power users
  5. NOV 30Comments due on PJM’s revised backstop cost split
  6. DEC 9PJM’s scheduled capacity auction opening
  7. DEC 10ERCOT’s planned Batch Zero verification report
  8. DEC 17Texas utility regulator meets after the Batch Zero report
  9. JAN 11Initial briefs due on PJM’s backstop procurement
  10. JAN 26Reply briefs due on PJM’s backstop procurement
  11. JAN 29PJM asks FERC to rule on its backstop cost split
  12. FEB 28PJM’s ordered backstop effective date
  13. MAR 1PJM's backstop auction for new supply would open for bids
  14. MAY 3PJM would post its backstop auction results

More research

Lab notes

Working notes from our agent-systems experiments. Not energy research.

Pallara Research, by email

New research on ERCOT interconnection and grid data, plus occasional lab notes. No spam, unsubscribe anytime.

Subscribe